§ 5-137. Rough inspection.  


Latest version.
  • When the rough wiring or installation work is completed on any premises, the person responsible therefor shall notify the electrical inspector that the job is ready for inspection, giving proper identification of the work, address and permit number. The electrical inspector shall then make an inspection of the electric installation within twenty-four (24) hours from the time of notification (exclusive of Saturday, Sunday and legal holidays). If the wiring or installation work has been installed in accordance with the terms and provisions of this article, the city electrical inspector shall sign a blue inspection card, noting thereon the date of approval of the work. More than one (1) rough inspection may be made without charge when the progress of construction requires such inspection.

(Ord. No. 68-12-2, ch. VII, § 2, 1-6-69)